Installation Procedures
Commissioning of Maxtend® System
After the container is loaded with cargo the Maxtend® system is commissioned.
1. CO2 scrubber pads (if required) are placed in position while loading
2. A plastic sealing curtain is fitted to prevent atmosphere leakage
3. Initial atmosphere established by gas flushing of container
4. Controller Installed and final pre check testing completed
5. Safety warning notice is placed on container prior to shipping
(note arrow in picture) |